The Cars Photographing Holliday's Streets Start a Plan With a Deadline

November 5, 2026

If a car rolls slowly down your block in Holliday on Tuesday, Nov. 10, or Thursday, Nov. 12, and someone inside stops to take photos, the City of Holliday is behind it. The City has partnered with Public Management, Inc. to prepare a Comprehensive Plan through the Texas General Land Office's Resilient Communities Program. The City's notice says the firm's staff will be in town on those two days "to conduct fieldwork and document existing conditions," and that residents "may see staff driving slowly, stopping along streets, and taking photographs throughout the community."

Under the state program paying for it, the plan has to be turned into an adopted rule about what can be built and where, and that has to happen within the grant's contract term. The photos taken this month are the first piece of evidence that rule will rest on.

What the program means by a "comprehensive plan"

The General Land Office's application guide for the program, published April 18, 2025, is direct about it. Comprehensive plans "take the community goals and aspirations and formalize them into actionable policies that determine what can be built within a certain jurisdiction and where." The same guide says a plan funded this way must be codified by adopting "a Zoning Ordinance or equivalent governing regulation or code provision." It describes a zoning ordinance as the step that takes the plan's ideas and codifies them "into a legally binding development regulation."

The guide lists five required parts: a population study, a housing study, a land use study and plan, a zoning ordinance, and an infrastructure study with a capital improvement plan. Burkburnett's request for planning consultants under the program describes each part in more detail.

Required element What it has to cover Where street-level fieldwork feeds in
Population study A current estimate and a 20-year projection Indirectly, as the baseline the projection grows from
Housing study Total units, single-family and multifamily counts, vacancy rates, and units needed 10 years out Existing housing stock seen from the street
Land use study and plan The land use of every parcel, plus a future land use map Parcel-by-parcel conditions across town
Zoning ordinance The rule that puts the land use plan into effect Built on the land use map above
Infrastructure study and capital improvement plan Water, wastewater, drainage, and streets, including length, width, materials, and condition or age where available, with prioritized improvements Street width, surface, and condition

The plan must also identify local hazard risks and explain how it addresses them, which follows from the program's focus on mitigation.

So the two days of photographs are not a general survey of how Holliday looks. They feed several of these documents, especially the parcel-level land use study and the street inventory.

The clock that comes with the money

The program offers grants of up to $300,000 from a $100 million statewide allocation. Applications closed December 31, 2025.

The application guide says adoption of the approved comprehensive plan and zoning ordinance "must be complete within the RCP grant contract term (approximately 3 years)." Burkburnett's request for consultants lists a tighter version of the requirement: adoption within 24 months of award, with failure to adopt resulting in "forfeiture of grant funds and repayment." Either way, the end point is written into the contract.

For anyone who owns a lot, plans to add a shop building, or watches open acreage around town, this is the practical point. A plan like this is supposed to end with a map of future land use and a regulation that puts it into effect. The current conditions recorded this month are the starting point for that map.

This post is general information, not legal advice. Anyone weighing how a future land use rule might affect a specific property should check with the City and the appropriate professional.

How it has gone in Electra and Graham

Two nearby cities are further along in the same program, and their records show roughly how long this takes.

Electra has a Resilient Communities Program activity to "develop and adopt a Comprehensive Plan." The General Land Office's report for October through December 2025 lists:

  1. Projected start: Feb. 28, 2025
  2. Projected end: April 30, 2029
  3. Total budget: $300,000
  4. Drawn and spent through Dec. 31, 2025: $105,000
  5. Required contents: hazard risks, population, housing, land use, and infrastructure studies, plus "zoning ordinances or similar to support the adoption of the Comprehensive Plan"

Graham is the closer comparison because it hired the same consultant. The City of Graham's plan page says the city applied in October 2024, received the award in March 2025, and selected Public Management Incorporated as managing consultant. Since then, the firm "has been conducting field work, compiling base studies, and administering a City-wide survey," and Graham expects to finish in 2027. Graham calls the result its Comprehensive Plan 2035 and has put progress updates and documents on a public web page built by Public Management.

Holliday's two days of driving and photographing are the same kind of fieldwork that is listed first in Graham's account of its process.

The systems the infrastructure study will inventory

The infrastructure study is the part of the plan closest to daily life in Holliday. It covers water, wastewater, drainage, and streets, and it has to end in a prioritized list of improvements.

Recent City Hall business already involves those same systems. On Monday, Oct. 19, the Holliday City Council approved a subscription agreement with SPMR for software that lets the city record utility meter data on smartphones, Archer County News reported. Public Works Director Danny Addison told the paper the software will speed up the meter and billing process. "This just allows us to use a smart phone to enter the data," Addison said.

On the streets side, the City posted notices on Sept. 21 for the 300 block of N Cedar. The first closed the block to through traffic for work, and the second said the work was finished and the street was back open. In a notice dated Aug. 31, the City also announced a repair at the elementary school parking lot exit, with a temporary closure starting Sept. 1 and expected to last no more than two weeks.

For now these are one-off repairs on single blocks. The capital improvement plan is meant to rank fixes like them across the whole town, using the street length, width, materials, and condition data that fieldwork like this month's collects.

Who to ask

The City's notice sends all questions about the fieldwork to Tiffanie Henson, City Secretary, at (940) 583-1202. Council agendas and minutes from 2025 onward are posted on the City of Holliday's agendas and minutes page, and future plan items will appear there. City notices, including this one, are posted on the City's public notice page.

If you're thinking about what a future land use map could mean for a lot you own or one you're considering in Holliday, McCown Real Estate LLC is glad to talk it through, follow the plan with you as drafts come out, and help you get the right people involved. Work With Us.