What’s Next for the Data Center Near Lakeside City on Three Way Road?

October 15, 2026

On September 28, dozens of Archer County residents filled the Lakeside City Community Center to talk about how to stop the data center proposed for Three Way Road. The same day, the Archer County Commissioners Court passed two resolutions opposing parts of the project. Two days later, County Judge Randall Jackson told the Times Record News how far those resolutions actually reach: "We really don't have any authority to stop those permits, but it (the resolutions) does put them on the radar."

That quote is the most useful thing to know about Project Raptor right now. The county already used its one real lever back in June. Every decision still open sits in Austin, and the next date that matters is a state deadline one week from today.

What was actually proposed for Three Way Road

Most of what's publicly known comes from an FAQ document that county officials released on Monday, April 27, 2026. Archer County News laid it out, and the document stressed that the plans were preliminary. Earlier that month, State Rep. James Frank told the Times Record News that Google had confirmed it was the proposed developer and operator of the site.

The April document described:

  • Site and investment: a 2,800-acre property on Three Way Road and a potential $1 billion capital investment. KFDX has since described the footprint as about 2,500 acres.
  • Jobs: about 50 full-time workers once it's running, with fewer than 1,000 construction workers at peak.
  • Power: demand of up to 1,000 megawatts through a direct connection to the Bowman switch station, with partial service expected by 2028 and full capacity by 2031, if ERCOT approves.
  • Water: a maximum of 32,000 gallons a day including domestic use, air cooling instead of water cooling, and about 9.5 miles of pipeline upgrades with Wichita Valley Water Supply, estimated at $3.5 million to $4.5 million and paid for by Google.
  • Noise and setbacks: a target of 65 decibels at the property lines and buildings set back at least 500 feet, which would put the nearest homes more than 1,200 feet away.

For anyone who drives US 79 every day, the road list is the detail most likely to change a commute. It includes paving and drainage on Three Way Road from FM 2224 to FM 1954. Pending TxDOT input, it also lists a full-depth rebuild of FM 2224 from Three Way Road to US 79, deceleration lanes at US 79 and FM 2224, and intersection work at FM 1954 and US 79.

The one lever Archer County held, and what using it gave up

On June 22, commissioners voted unanimously against a proposed tax abatement for Dynamo Ventures LLC, the company developing the project. More than 30 residents came to that meeting to speak against the incentive. KAUZ reported that the vote did not itself block the development.

Saying no also meant giving something up. County officials said an abatement could have given Archer County leverage in negotiations, possibly helping it secure infrastructure improvements, local hiring and other commitments from the developer. Judge Jackson explained the denial as a decision to wait for Austin first. "The Texas Legislature may put some restrictions on how they operate before, during and after the construction and I would like to see what those restrictions are going to be," he said.

So the county's own explanation of its main decision pointed to the state. Everything since then has moved the same way.

Two wastewater permits and a number that hasn't been explained

Over the summer the action shifted to the Texas Commission on Environmental Quality. Dynamo Ventures filed two applications. One, WQ0017005001, is a TPDES permit for a wastewater treatment plant. The other, WQ0016998001, is a Texas Land Application Permit. The Times Record News reported in August that the discharge permit would allow up to 95,000 gallons a day into Lake Wichita, and that the application describes the plant as serving "employee sanitary wastewater needs at the site." The land application permit would allow discharge directly onto the Three Way Road property.

Here are the two figures side by side. In April, the facility was described as using at most 32,000 gallons of water a day in total. In the summer filing, the discharge figure is 95,000 gallons a day. None of the coverage so far explains why the discharge ceiling is nearly three times the stated maximum use. The April document also said wastewater would first go to an evaporation pond until state permits for direct stream discharge were approved, so stream discharge was in the plan from the start.

Coverage says the treated water would reach Lake Wichita through open tributaries. The specific creek hasn't been named in any reporting this office has reviewed.

The county's September 28 resolutions responded to this permit stage. One opposes the two wastewater permits and says the project "may place substantial demands on local and regional natural water resources, electric infrastructures, roads, drainage systems, wastewater capacity, emergency services, and other public resources." The other asks TCEQ to reevaluate an already-approved permit for City Concrete Inc. to run a concrete batch plant at the site, citing water used for dust control and the effect of cement and ash dust on air quality. The county has also asked that any TCEQ hearing be held in Archer County.

How the TCEQ process works

Since the open questions are now state questions, the state's process is worth understanding. TCEQ publishes a Notice of Receipt and Intent once an application is administratively complete. After technical review and a draft permit, it publishes a Notice of Application and Preliminary Decision. For most applications, public comments can be filed from the first notice through 30 days after the second. A public meeting has to be requested in writing to the Chief Clerk during the comment period. At that meeting, people can ask questions and comment, but the meeting does not decide whether the permit is issued. A contested case hearing is a separate step. The requester has to show they're an "affected person" who is impacted differently from the general public on an issue TCEQ regulates. TCEQ's guide to contested case hearings explains what that request has to contain.

We haven't been able to confirm where these two applications are in that sequence. We haven't found the notice dates, a comment deadline, or whether a TCEQ public meeting has been scheduled. TCEQ stopped updating its older pending-applications page on September 14, 2026, and now points to its Permit Search Portal for application documents. KFDX linked TCEQ's eComment page for residents who want to comment online. This is a general explanation of a state process, not legal advice. Anyone weighing a formal hearing request should confirm the details with TCEQ or an attorney.

The decision that outranks all of it

On September 21, a week before the Lakeside City meeting, Governor Greg Abbott directed TCEQ to "halt all permits sought by data centers" until ERCOT finishes its audit. The directive said no state agency should move forward on data center approvals until that information is in hand. It also says data centers "must not use water needed by local communities," must report their water and electricity use, and must follow setback requirements. TCEQ has to report its compliance to the governor by Monday, October 19, 2026. Abbott also said he will work with the Legislature next session to eliminate financial incentives for data centers.

Archer County's resolution says it "fully supports and aligns with" that directive. The coverage we reviewed doesn't confirm how TCEQ is applying the freeze to these two applications specifically.

The freeze is already slowing a second project in the area. Skybox Data Centers is planning the Skybox Power Campus on a 225-acre parcel at Wichita Falls Business Park. On October 6, Skybox told the Wichita Falls City Council that the state audits had pushed its groundbreaking from late 2026 into the first quarter of 2027, and that it still plans to comply. Rep. Frank supports the Skybox project and opposes the Three Way Road site, and he draws the line at location. "Location matters when you're putting in these data center projects," he told KFDX, adding that he has contacted the governor's office and TCEQ and plans to pursue legislation.

The Skybox campus has a business park site and city backing, and the state audit still pushed its schedule back by months.

The calendar from here

Date What happens Who decides
June 22, 2026 Tax abatement denied Archer County Commissioners Court
Aug. 25, 2026 95,000-gallon-per-day discharge application reported TCEQ, under review
Sept. 21, 2026 Data center permit freeze ordered Governor's office
Sept. 28, 2026 Two county resolutions; resident meeting in Lakeside City County, residents
Oct. 19, 2026 TCEQ compliance report to the governor due TCEQ
January 2027 Legislative session begins Texas Legislature

Organizers with Stop the Archer County Data Center have urged residents to submit public comments before the session opens in January. In our review of coverage from October 1 through today, we found no report that the project has been withdrawn or paused, and no new statement from Google. The next confirmed date is TCEQ's report to the governor, due a week from today, on October 19.

Questions about how Project Raptor or the road work around FM 2224 and US 79 could affect a property near Three Way Road deserve straight answers from people who follow it closely. The team at McCown Real Estate LLC tracks these filings and deadlines as they happen and is glad to walk you through what's on the record. Work With Us.